    We have a few PM’s that have been set up to the incorrect locations, I would like to move the Work Order history to the correct Locations.

    I assume that changing the Workview location field would do the trick.

    David

    #5226
    DVaucher
    Participant

    Just realised there is no location field in the Workview table,  basically we have PMs that are on the incorrect locations, I would like to update the PM to the correct location and move all history to the new location (specifically meter readings)

    Is it as simple as updating the measurement table location field to the new location?