PM to trigger work every 6 months or every 300 hours, whichever comes first.

From: comprateur (2012-08-07 09:48)

Hello,
is it possible to have a PM with both calendar and running hours or odometer in order to have a PM triggering a work every 6 months or every 300 hours, whichever comes first.
Can you explain the steps and it works?
Thanks,


From: Pat Morrow (2012-08-07 10:55)

Ensure the asset has a meter attached.
 
Create the PM on the asset.
Go to the frequency tab
    On the Time Based Frequency subtab - put 6 in the Frequency field and MONTHS in the Units field (and populate/change any of the other values on this tab based on your business rules)
    On the Meter Base Frequency subtab - insert new row and fill in the fields.
Set the PM to active.
 
PM will generate a workorder if either of the values set above are met.  Both meter and time are reset when workorder is created/completed - based on the selection in the PM.
Pat Morrow
pmorrow8@yahoo.com

________________________________
From: comprateur <comprateur@yahoo.fr>
To: "MAXIMO@yahoogroups.com" <MAXIMO@yahoogroups.com>
Sent: Tuesday, August 7, 2012 2:48 AM
Subject: [MAXIMO List] PM to trigger work every 6 months or every 300 hours, whichever comes first.


 

Hello,
is it possible to have a PM with both calendar and running hours or odometer in order to have a PM triggering a work every 6 months or every 300 hours, whichever comes first.
Can you explain the steps and it works?
Thanks,