Naming PM, Routes and Job plans

From: Javaid Ansari (2014-03-26 14:47)

Hello All,
 
We are planning to configure Job Plans, Routes and PMs in Maximo 7.5 oil and gas.
 
What will be the best practice for naming these activities? Objective is to have intelligent name which can give brief detail on the contents.
In the older system currently planners and maintenace team have created multitude of records which are not manageable.
The asset types we are dealing with are: MECHANICAL, EI&C/SCADA, PIPELINE, TANK, PSV, PV.
Thanks
Javaid Ansari


From: Egolf, Kevin (TechOps Solutions, International) (2014-03-27 00:56)

Why would you use intelligent names when there many other fields available on the records to do that. You can use classifications, one of the other existing fields or add a new field and a domain to group your records. Intelligent names are difficult to maintain and manage over time. Your current system is a good example of that
.
Kevin
________________________________
From: MAXIMO@yahoogroups.com [MAXIMO@yahoogroups.com] on behalf of Javaid Ansari [javaidansari@yahoo.com]
Sent: Wednesday, March 26, 2014 5:47 PM
To: MAXIMO@yahoogroups.com
Subject: [External] [MAXIMO List] Naming PM, Routes and Job plans
Hello All,
We are planning to configure Job Plans, Routes and PMs in Maximo 7.5 oil and gas.
What will be the best practice for naming these activities? Objective is to have intelligent name which can give brief detail on the contents.
In the older system currently planners and maintenace team have created multitude of records which are not manageable.
The asset types we are dealing with are: MECHANICAL, EI&C/SCADA, PIPELINE, TANK, PSV, PV.
Thanks
Javaid Ansari


From: Ian Wright (2014-03-27 09:28)

Agreed use classification intelligently :)
Ian
From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of Egolf, Kevin (TechOps Solutions, International)
Sent: 27 March 2014 00:57
To: MAXIMO@yahoogroups.com
Subject: RE: [External] [MAXIMO List] Naming PM, Routes and Job plans
Why would you use intelligent names when there many other fields available on the records to do that. You can use classifications, one of the other existing fields or add a new field and a domain to group your records. Intelligent names are difficult to maintain and manage over time. Your current system is a good example of that
.
Kevin
________________________________
From: MAXIMO@yahoogroups.com<mailto:MAXIMO@yahoogroups.com> [MAXIMO@yahoogroups.com] on behalf of Javaid Ansari [javaidansari@yahoo.com]
Sent: Wednesday, March 26, 2014 5:47 PM
To: MAXIMO@yahoogroups.com<mailto:MAXIMO@yahoogroups.com>
Subject: [External] [MAXIMO List] Naming PM, Routes and Job plans
Hello All,
We are planning to configure Job Plans, Routes and PMs in Maximo 7.5 oil and gas.
What will be the best practice for naming these activities? Objective is to have intelligent name which can give brief detail on the contents.
In the older system currently planners and maintenace team have created multitude of records which are not manageable.
The asset types we are dealing with are: MECHANICAL, EI&C/SCADA, PIPELINE, TANK, PSV, PV.
Thanks
Javaid Ansari
GDF SUEZ E&P UK Ltd (Company Number 3386464), registered in England and Wales with a registered office address at: 40 Holborn Viaduct, London, EC1N 2PB.
**************************************************************************************************************
This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed.
If you have received this email in error please notify the system manager.
**************************************************************************************************************


From: (2014-03-28 12:35)

I would agree strongly with Kevin's response. Too often people get mired in coding too much data into 1 field. Utilize the powerful database as it was intended, multiple fields for containing varied information. Your freedom later will not be constrained by field length, abbreviations, etc.


From: Klemenok, Eric (2014-03-31 12:29)

Classifications are the cleanest and most powerful solution you have for organizing what is often pretty complex data.
Most people never touch Classifications….which is a shame because it’s standard functionality that’s just sitting there.

From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of sschaurer@gmail.com
Sent: Friday, March 28, 2014 2:36 PM
To: MAXIMO@yahoogroups.com
Subject: RE: [External] [MAXIMO List] Naming PM, Routes and Job plans



I would agree strongly with Kevin's response. Too often people get mired in coding too much data into 1 field. Utilize the powerful database as it was intended, multiple fields for containing varied information. Your freedom later will not be constrained by field length, abbreviations, etc.