I did think that, logically, I should be able to set it up as a two-month frequency, between April and October, with the startup/shutdown plans happening as they naturally should. This works for a year, but then I think it falls apart because the counter will not increment unless it produces a work order, and it doesn't produce a work order in December or February.
I really want it to be one PM instead of two, but I cannot figure out how.
Month
Plan
Sequence
Counter
June
Operational check
1
1
August
Operational check
1
2
October
Shutdown
3
3
April
Startup
4
4
June
Operational check
1
5
August
Operational check
3
6
October
Shutdown
1
7
April
Startup
4
8
Miranda Anderson, MPP
Business Analyst, Facilities Department
Calgary Catholic School District
1000 - 5th Avenue SW, Calgary, AB T2P 4T9
Email: miranda.anderson@cssd.ab.ca<mailto:miranda.anderson@cssd.ab.ca>
Mobile: 403.990.5998
Office: 403.500.2753
"Success is neither magical nor mysterious. Success is the natural consequence of consistently applying the basic fundamentals." -- Jim Rohn