Use lead time when reservation is made on work order

From: Ron Sleijpen (2012-03-21 10:00)

Dear group,

I am looking for a solution of the use of the lead (delivery time) time
when reordering items by reservation on work orders.

When items are issued and the min level is reached, the item is
reordered and the lead time is used to calculate the required date.
So when lead time is 5 and I reorder today, the required date in the
requisition will be: today + 5 = 26-3-2012.

But when an item is reserved on a work order and the item is reordered,
the lead time is NOT used in the required date.
The required date is ALWAYS "today" (the day that the reordering is
done).

Is there anybody who knows if there's a setting that the leadtime is
also used in these cases?
Or another working method that the required date is NOT the date of
today?

Many thanks.

Ron Sleijpen
Royal Mosa
Netherlands

The contents of this e-mail and attachments, if any, is confidential and only intended for the person(s) to which it is addressed. If you receive this e-mail in error then we kindly request you to inform the sender thereof immediately, and to delete the e-mail and the attachments without printing, copying or distributing any of those.
The publication, copying whole or in part or use or dissemination in any other way of the e-mail and attachments by others than the intended person(s) is prohibited. Koninklijke Mosa BV cannot guarantee the security of electronic communication and is not liable for any negative consequence of the use of electronic communication, including but not limited to, damage as a result of in or non-complete delivery or delay in delivery of any e-mail; the text of the e-mail as sent is decisive. Nor can be guaranteed that this message is free from viruses.
On all our sales offers and email communication regarding sales offers applies our General Conditions of Delivery and Payment of Koninklijke Mosa BV. A copy of these conditions is filed in Dutch language at the Chamber of Commerce in Maastricht. A copy of the General Conditions of Delivery and Payment of Koninklijke Mosa BV is available at
WWW.MOSA.NL and on request a copy will be sent to you by post, fax or email, free of charge.
On all our purchase orders and email communication regarding purchase orders applies our General Terms and Conditions of Purchase of Koninklijke Mosa BV. A copy of these conditions is filed in Dutch language at the Chamber of Commerce in Maastricht. On request a copy of these conditions will be sent to you by post, fax or email, free of charge.
Koninklijke Mosa BV, Meerssenerweg 358, 6224 AL Maastricht, The Netherlands, Chambre of Commerce nr. 14600086


From: Pat Morrow (2012-03-21 06:14)

Or another working method that the required date is NOT the date of
today?
Have the users enter the 'Scheduled Start' date on the main page of the Workorder before they enter materials on the 'Plan tab'.  It will them default to that date instead of current date.
Pat Morrow
pmorrow8@yahoo.com
________________________________
From: Ron Sleijpen <ron.sleijpen@mosa.nl>
To: MAXIMO@yahoogroups.com
Sent: Wednesday, March 21, 2012 5:00 AM
Subject: [MAXIMO List] Use lead time when reservation is made on work order
 
Dear group,
I am looking for a solution of the use of the lead (delivery time) time
when reordering items by reservation on work orders.
When items are issued and the min level is reached, the item is
reordered and the lead time is used to calculate the required date.
So when lead time is 5 and I reorder today, the required date in the
requisition will be: today + 5 = 26-3-2012.
But when an item is reserved on a work order and the item is reordered,
the lead time is NOT used in the required date.
The required date is ALWAYS "today" (the day that the reordering is
done).
Is there anybody who knows if there's a setting that the leadtime is
also used in these cases?
Or another working method that the required date is NOT the date of
today?
Many thanks.
Ron Sleijpen
Royal Mosa
Netherlands
The contents of this e-mail and attachments, if any, is confidential and only intended for the person(s) to which it is addressed. If you receive this e-mail in error then we kindly request you to inform the sender thereof immediately, and to delete the e-mail and the attachments without printing, copying or distributing any of those.
The publication, copying whole or in part or use or dissemination in any other way of the e-mail and attachments by others than the intended person(s) is prohibited. Koninklijke Mosa BV cannot guarantee the security of electronic communication and is not liable for any negative consequence of the use of electronic communication, including but not limited to, damage as a result of in or non-complete delivery or delay in delivery of any e-mail; the text of the e-mail as sent is decisive. Nor can be guaranteed that this message is free from viruses.
On all our sales offers and email communication regarding sales offers applies our General Conditions of Delivery and Payment of Koninklijke Mosa BV. A copy of these conditions is filed in Dutch language at the Chamber of Commerce in Maastricht. A copy of the General Conditions of Delivery and Payment of Koninklijke Mosa BV is available at
WWW.MOSA.NL and on request a copy will be sent to you by post, fax or email, free of charge.
On all our purchase orders and email communication regarding purchase orders applies our General Terms and Conditions of Purchase of Koninklijke Mosa BV. A copy of these conditions is filed in Dutch language at the Chamber of Commerce in Maastricht. On request a copy of these conditions will be sent to you by post, fax or email, free of charge.
Koninklijke Mosa BV, Meerssenerweg 358, 6224 AL Maastricht, The Netherlands, Chambre of Commerce nr. 14600086