Maximo Scheduler Version 7

From: morgan (2011-06-29 16:45)

Hi all
Has anyone out there have any experiences with Maximo scheduler> I was reading some of the online documents and was couldn't tell by the way they described it as a client application.
I know is gets installed on the appserver but is it then have a client
piece installed on the machines of the users that want it or is it just
acessed by Security rights.
The main reason is that my planners want the ability to change the Scheduled start date of a number of work orders in one shot.
When PMs are generated we get the Target Start Date but they want to change the Scheduled Start date on them in Wotrack.
Thanks in advance
Ray DeFelice
PWD


From: jhon fredy (2012-01-23 00:22)

Bueno, nosotros tambien manadmos a cambiar la fecha prevista por la fecha programada,pero creoque no se puede cambiar la fecha programada a todas las ordenes de trabajo.
Saludos
--- In MAXIMO@yahoogroups.com, "morgan" <morgan19153@...> wrote:
>
> Hi all
>
> Has anyone out there have any experiences with Maximo scheduler> I was reading some of the online documents and was couldn't tell by the way they described it as a client application.
>
> I know is gets installed on the appserver but is it then have a client
> piece installed on the machines of the users that want it or is it just
> acessed by Security rights.
>
> The main reason is that my planners want the ability to change the Scheduled start date of a number of work orders in one shot.
> When PMs are generated we get the Target Start Date but they want to change the Scheduled Start date on them in Wotrack.
>
> Thanks in advance
>
> Ray DeFelice
> PWD
>


From: Michael Dougherty (2012-01-24 11:45)

We are trying the scheduler out now. Access is done through the security groups. Just make sure all of your labor has a calendar assigned to them, otherwise when you generate PMs with the laborcodes attached, you will receive error messages.
From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of jhon fredy
Sent: Sunday, January 22, 2012 7:23 PM
To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] Re: Maximo Scheduler Version 7
Bueno, nosotros tambien manadmos a cambiar la fecha prevista por la fecha programada,pero creoque no se puede cambiar la fecha programada a todas las ordenes de trabajo.
Saludos
--- In MAXIMO@yahoogroups.com<mailto:MAXIMO%40yahoogroups.com>, "morgan" <morgan19153@...<mailto:morgan19153@...>> wrote:
>
> Hi all
>
> Has anyone out there have any experiences with Maximo scheduler> I was reading some of the online documents and was couldn't tell by the way they described it as a client application.
>
> I know is gets installed on the appserver but is it then have a client
> piece installed on the machines of the users that want it or is it just
> acessed by Security rights.
>
> The main reason is that my planners want the ability to change the Scheduled start date of a number of work orders in one shot.
> When PMs are generated we get the Target Start Date but they want to change the Scheduled Start date on them in Wotrack.
>
> Thanks in advance
>
> Ray DeFelice
> PWD
>