Maintaining PM schedule when WOs are late

From: c_westberry (2011-07-20 15:58)

Is it possible to prevent the WO generation feature from updating the Earliest next due date? We recently ran into a situation where a few PMs were late being generated, and this caused all future generations to push back the same amount. We want the target date to stay the 1st of the month, but if we don't generate this month's WO until the 3rd, MX pushes the next due date and all future dates to the 3rd of the month. There's got to be a simple fix, but I haven't located it yet. Thanks!
Chris W.