Reorder, Direct Issue Materials and Services, Default Grouping of Resulting PRs

From: sarah_locke_stewart (2011-12-13 19:13)

Hi,
Does anyone know of a way to change the way in which Maximo groups the resulting PRs when Reorder is run for Direct Issue Materials and Services. Out of the box behavior is to group by Vendor....we'd like the resulting PRs to be group by Work Order Number.
Thanks,
Sarah


From: Shannon Rotz (2011-12-13 19:37)

No idea - and I'd like to know the answer to that one myself!


Shannon

From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of
sarah_locke_stewart
Sent: December-13-11 11:14 AM
To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] Reorder, Direct Issue Materials and Services, Default
Grouping of Resulting PRs


Hi,
Does anyone know of a way to change the way in which Maximo groups the
resulting PRs when Reorder is run for Direct Issue Materials and Services.
Out of the box behavior is to group by Vendor....we'd like the resulting PRs
to be group by Work Order Number.
Thanks,
Sarah


From: Ashfaque Ahmed (2011-12-14 02:41)

Hi,
 
This functionality available through MR , it runs reorder specific to MR and vendor ,but this functionality is not available from work order , you need to run-reorder for direct material and services and PR will be created by Vendor.
 
We have put some customization on work order to group PR by vendor and work order .
 
 
Regards,
Ashfaque Ahmed
--- On Tue, 12/13/11, Shannon Rotz <shannonrotz@yahoo.ca> wrote:
From: Shannon Rotz <shannonrotz@yahoo.ca>
Subject: RE: [MAXIMO List] Reorder, Direct Issue Materials and Services, Default Grouping of Resulting PRs
To: MAXIMO@yahoogroups.com
Date: Tuesday, December 13, 2011, 7:37 PM
 
No idea - and I'd like to know the answer to that one myself!
Shannon
From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of
sarah_locke_stewart
Sent: December-13-11 11:14 AM
To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] Reorder, Direct Issue Materials and Services, Default
Grouping of Resulting PRs
Hi,
Does anyone know of a way to change the way in which Maximo groups the
resulting PRs when Reorder is run for Direct Issue Materials and Services.
Out of the box behavior is to group by Vendor....we'd like the resulting PRs
to be group by Work Order Number.
Thanks,
Sarah


From: ron_bryant (2011-12-14 08:06)

How did you do your customization? Custom Class or is there some other way? We would like to do the same thing.

Ron Bryant
IT Business Consultant
Plant Systems & Controls
Cargill
direct - 651-203-7947 | mobile - 612-801-7658
ron_bryant@cargill.com

"Confidentiality Note: This message is intended only for the named recipient and may contain confidential, proprietary or legally privileged information. Unauthorized individuals or entities are not permitted access to this information. Any dissemination, distribution, or copying of this information is strictly prohibited. If you have received this message in error, please advise the sender by reply e-mail, and delete this message and any attachments. Thank you."

From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of ashfaqque_ahmed@yahoo.com
Sent: Wednesday, December 14, 2011 4:41 AM
To: MAXIMO@yahoogroups.com
Subject: RE: [MAXIMO List] Reorder, Direct Issue Materials and Services, Default Grouping of Resulting PRs



Hi,

This functionality available through MR , it runs reorder specific to MR and vendor ,but this functionality is not available from work order , you need to run-reorder for direct material and services and PR will be created by Vendor.

We have put some customization on work order to group PR by vendor and work order .


Regards,
Ashfaque Ahmed

--- On Tue, 12/13/11, Shannon Rotz <shannonrotz@yahoo.ca<mailto:shannonrotz%40yahoo.ca>> wrote:

From: Shannon Rotz <shannonrotz@yahoo.ca<mailto:shannonrotz%40yahoo.ca>>
Subject: RE: [MAXIMO List] Reorder, Direct Issue Materials and Services, Default Grouping of Resulting PRs
To: MAXIMO@yahoogroups.com<mailto:MAXIMO%40yahoogroups.com>
Date: Tuesday, December 13, 2011, 7:37 PM



No idea - and I'd like to know the answer to that one myself!

Shannon

From: MAXIMO@yahoogroups.com<mailto:MAXIMO%40yahoogroups.com> [mailto:MAXIMO@yahoogroups.com<mailto:MAXIMO%40yahoogroups.com>] On Behalf Of
sarah_locke_stewart
Sent: December-13-11 11:14 AM
To: MAXIMO@yahoogroups.com<mailto:MAXIMO%40yahoogroups.com>
Subject: [MAXIMO List] Reorder, Direct Issue Materials and Services, Default
Grouping of Resulting PRs

Hi,

Does anyone know of a way to change the way in which Maximo groups the
resulting PRs when Reorder is run for Direct Issue Materials and Services.
Out of the box behavior is to group by Vendor....we'd like the resulting PRs
to be group by Work Order Number.

Thanks,

Sarah