HI all
I was looking at the IBM test site vertiosn 7.5 and I didn't see a field in the Tolls App for putting in an hourly rate or a cost for each. I saw the purchase price field on the vendor tab.
I used on the their exisitng records and put in 15000 for a Clark Forl lift as the puchase price.
When I put it on a job plan for 2 hours of use it showd the hourly rate of $2.40.
Am I missing something here?
Ray DeFelice
Tool Rate is set by:
Go To > Inventory > Tools
Pull up the tool that you are interested in setting/checking the rate for.
Select Action > Tool/Organization Details
You can fill in a default rate and/or default GL Account by Organization.
This is where the rate is pulled from on the WorkPlan Tool tab.
Pat Morrow
pmorrow8@yahoo.com
________________________________
From: morgan <morgan19153@yahoo.com>
To: MAXIMO@yahoogroups.com
Sent: Thursday, March 8, 2012 9:40 AM
Subject: [MAXIMO List] Hourly rate for Tools in Version 7.5
HI all
I was looking at the IBM test site vertiosn 7.5 and I didn't see a field in the Tolls App for putting in an hourly rate or a cost for each. I saw the purchase price field on the vendor tab.
I used on the their exisitng records and put in 15000 for a Clark Forl lift as the puchase price.
When I put it on a job plan for 2 hours of use it showd the hourly rate of $2.40.
Am I missing something here?
Ray DeFelice
thank you so much!
--- In MAXIMO@yahoogroups.com, Pat Morrow <pmorrow8@...> wrote:
>
> Tool Rate is set by:
> Go To > Inventory > Tools
> Pull up the tool that you are interested in setting/checking the rate for.
> Select Action > Tool/Organization Details
> You can fill in a default rate and/or default GL Account by Organization.
> This is where the rate is pulled from on the WorkPlan Tool tab.
>
> Pat Morrow
> pmorrow8@...
>
>
>
> ________________________________
> From: morgan <morgan19153@...>
> To: MAXIMO@yahoogroups.com
> Sent: Thursday, March 8, 2012 9:40 AM
> Subject: [MAXIMO List] Hourly rate for Tools in Version 7.5
>
>
> Â
> HI all
>
> I was looking at the IBM test site vertiosn 7.5 and I didn't see a field in the Tolls App for putting in an hourly rate or a cost for each. I saw the purchase price field on the vendor tab.
>
> I used on the their exisitng records and put in 15000 for a Clark Forl lift as the puchase price.
>
> When I put it on a job plan for 2 hours of use it showd the hourly rate of $2.40.
>
> Am I missing something here?
>
> Ray DeFelice
>
>
>
>
>
>
Hi,
We have Maximo 7.1.18 and tool rate is defined in Tools>Select Action>Tool Organization Details. Hope this is still the case for 7.5.
Thanks
________________________________
From: morgan <morgan19153@yahoo.com>
To: MAXIMO@yahoogroups.com
Sent: Friday, 9 March 2012 1:40 AM
Subject: [MAXIMO List] Hourly rate for Tools in Version 7.5
HI all
I was looking at the IBM test site vertiosn 7.5 and I didn't see a field in the Tolls App for putting in an hourly rate or a cost for each. I saw the purchase price field on the vendor tab.
I used on the their exisitng records and put in 15000 for a Clark Forl lift as the puchase price.
When I put it on a job plan for 2 hours of use it showd the hourly rate of $2.40.
Am I missing something here?
Ray DeFelice