how to modify Extended date in Master PM

From: mark.dong (2012-07-31 01:27)

Hi All,
I have created some master PM and generate pm, work order by master pm. Currently the Estimated next due date is 3-Sept-2012,
I want to change it to 10-Aug-2012 by modifing the Extended date and Adjust Next Due Date of Master PM , but the two field are readonly. it's only "next Due Date (Used During PM Create Only): " field can be edited.
Please tell me how to modify the Extended date and Adjust Next Due Date of Master PM?
what's meaning about the "next Due Date (Used During PM Create Only)" (also need to input the "10-Aug-2012" value?)
Thanks in advance