PO required date does not carry over to the POLINE required date

From: cbrandon63 (2012-10-04 16:35)

Maximo 7.5.0
When a required date is entered on the PO it is not carrying over to the POLINE ... which is our desired functionality.
Does someone have a solution for this?


From: john reeve (2012-10-04 17:37)

Of course a given POline could have different dates.
You're probably after a default though.

Simple fix is to handle it inside the Report code.

W/br
jr
Sent on the Sprint� Now Network from my BlackBerry�

-----Original Message-----
From: "cbrandon63" <cbrandon63@yahoo.com>
Sender: MAXIMO@yahoogroups.com
Date: Thu, 04 Oct 2012 16:35:23
To: <MAXIMO@yahoogroups.com>
Reply-To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] PO required date does not carry over to the POLINE required date

Maximo 7.5.0
When a required date is entered on the PO it is not carrying over to the POLINE ... which is our desired functionality.

Does someone have a solution for this?