Generate PM's 3 weeks in advance

From: karoleigh.miller (2012-10-24 16:16)

I am very new to maximo and would like to generate only certain PM's assigned to a persongroup 3 weeks in advance of the due date...is there any "easy" way to do this?
any advice would be helpful!
K


From: Pat Morrow (2012-10-24 18:01)

Fill in the lead time of 21 days on the main page of the PMs that you wish to generate early.  (Check box below this field must be checked if I recall correctly - I am not in front of my work computer right now.)  If you have others that you want to generate a week early, put a lead time of 7 days, etc..
Make sure that you do not have a forecast for these PMs, as then it ignores the lead time.
Pat Morrow
pmorrow8@yahoo.com
From: karoleigh.miller <karoleigh.miller@york.ca>
To: MAXIMO@yahoogroups.com
Sent: Wednesday, October 24, 2012 12:16 PM
Subject: [MAXIMO List] Generate PM's 3 weeks in advance
 
I am very new to maximo and would like to generate only certain PM's assigned to a persongroup 3 weeks in advance of the due date...is there any "easy" way to do this?
any advice would be helpful!
K


From: karoleigh.miller (2012-10-25 16:29)

Thank you!
--- In MAXIMO@yahoogroups.com, Pat Morrow <pmorrow8@...> wrote:
>
> Fill in the lead time of 21 days on the main page of the PMs that you wish to generate early.  (Check box below this field must be checked if I recall correctly - I am not in front of my work computer right now.)  If you have others that you want to generate a week early, put a lead time of 7 days, etc..
> Make sure that you do not have a forecast for these PMs, as then it ignores the lead time.
>
> Pat Morrow
> pmorrow8@...
>
>
> From: karoleigh.miller <karoleigh.miller@...>
> To: MAXIMO@yahoogroups.com
> Sent: Wednesday, October 24, 2012 12:16 PM
> Subject: [MAXIMO List] Generate PM's 3 weeks in advance
>
>  
> I am very new to maximo and would like to generate only certain PM's assigned to a persongroup 3 weeks in advance of the due date...is there any "easy" way to do this?
>
> any advice would be helpful!
> K
>
>
>
>
>
>


From: Juniko (2012-10-27 09:06)

There is an organisation setup to do for this purpose also...if we'd like
to have our PM to generate automatically by a crontask, we should set the
lead time by 21 days.
Warm Regards,
Juniko W
On Oct 25, 2012 8:02 AM, "Pat Morrow" <pmorrow8@yahoo.com> wrote:
> **
>
>
> Fill in the lead time of 21 days on the main page of the PMs that you wish
> to generate early. (Check box below this field must be checked if I recall
> correctly - I am not in front of my work computer right now.) If you have
> others that you want to generate a week early, put a lead time of 7 days,
> etc..
> Make sure that you do not have a forecast for these PMs, as then it
> ignores the lead time.
>
> Pat Morrow
> pmorrow8@yahoo.com
>
> From: karoleigh.miller <karoleigh.miller@york.ca>
> To: MAXIMO@yahoogroups.com
> Sent: Wednesday, October 24, 2012 12:16 PM
> Subject: [MAXIMO List] Generate PM's 3 weeks in advance
>
>
> I am very new to maximo and would like to generate only certain PM's
> assigned to a persongroup 3 weeks in advance of the due date...is there any
> "easy" way to do this?
>
> any advice would be helpful!
> K
>
>
>
>
>