Maximo List Archive

This is an archive of the Maximo Yahoo Community. The content of this pages may be a sometimes obsolete so please check post dates.
Thanks to the community owner Christopher Wanko for providing the content.



Task Workorder numbers

From: George (2012-10-31 15:29)

Hello everyone,
When creating the workorder and you create a plan for the job can the task workorder number be disabled?
Maximo Oil and Gas 6.2.1
Weblogic
SQL 2005
Thx,
mrggutz


From: Mark Dong (2012-11-01 20:13)

Hi,
    You cannot disable the Task's work order number , but you can create new autokey for workorder's
task(Table : woactivity) in database configuration management
Mark
________________________________
From: George <ggutierrez@pasadenarefining.com>
To: MAXIMO@yahoogroups.com
Sent: Wednesday, October 31, 2012 11:29 PM
Subject: [MAXIMO List] Task Workorder numbers

 
Hello everyone,
When creating the workorder and you create a plan for the job can the task workorder number be disabled?
Maximo Oil and Gas 6.2.1
Weblogic
SQL 2005
Thx,
mrggutz


From: Bill (2012-11-05 21:09)

Mr Gutz:
There definitely are some options for you. Can you give me some more details behind why you're asking this so I can recommend a solution?
Bill Murphy
v7.1.1.6 / CAL 7.1
--- In MAXIMO@yahoogroups.com, "George" <ggutierrez@...> wrote:
>
> Hello everyone,
> When creating the workorder and you create a plan for the job can the task workorder number be disabled?
>
> Maximo Oil and Gas 6.2.1
> Weblogic
> SQL 2005
>
>
> Thx,
> mrggutz
>


From: Will Hampton (2012-11-05 21:47)

If you are referring to the 'reference WO' - the answer is no. The Tasks are actually Work Orders in the system, the only difference that actually exists between an "Regular" Work Order and a task is the "istask" flag on the row (and in later versions of Maximo like yours - a "woclass" of ACTIVITY)...
Since the Work Order number "wonum" is part of the primary key for all Work Order records - it must be provided and cannot be disabled.
You can however hide them if you really, really needed to... (makes it hard to do a lot of things - like add jobplans to the task... though...)
R/
Will
From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of Bill
Sent: Monday, November 05, 2012 3:09 PM
To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] Re: Task Workorder numbers
Mr Gutz:
There definitely are some options for you. Can you give me some more details behind why you're asking this so I can recommend a solution?
Bill Murphy
v7.1.1.6 / CAL 7.1
--- In MAXIMO@yahoogroups.com<mailto:MAXIMO%40yahoogroups.com>, "George" <ggutierrez@...<mailto:ggutierrez@...>> wrote:
>
> Hello everyone,
> When creating the workorder and you create a plan for the job can the task workorder number be disabled?
>
> Maximo Oil and Gas 6.2.1
> Weblogic
> SQL 2005
>
>
> Thx,
> mrggutz
>