Characteristics of a Small Site – and - work order scheduling
1)This organization has a very small work force. Operations and Maintenance staff are combined craft code, e.g. O&M Tech.
2)They do not have a large backlog
3)Most work is similar in nature & size.
4)There can be different skillsets but these are managed at morning stand-up
5)Supervisor needs to highlight Operational events as well as maintenance activities
6)Supervisor may identify a maintenance action but not give it a WO number until later. He will link to WONUM before job start however.
7)Supervisor may link a Crew, Craft or Worker to this task
8)Supervisor easily relates to a Calendar style format such as standard MS Outlook calendar.
9)Supervisor places work on calendar and does leveling in his head. Does not need to see barchart or histogram.