Maximo List Archive

This is an archive of the Maximo Yahoo Community. The content of this pages may be a sometimes obsolete so please check post dates.
Thanks to the community owner Christopher Wanko for providing the content.



Job Plan Duration vs. labor hours

From: Thomas (2013-01-30 16:32)

We are having the debate about job plan duration and planned labor hours on a job plan. Maximo doesn't have a very clear definition of what the duration is other than how many hours it will take to complete the work. Does/should this include time when work is not being
For example there is a work order to paint a small room with 2 coats of paint. Planning for 1 painter and 1 hour of labor for each coat we have 2 total labor hours. Is that the Duration? Or should we account for 2 hours of drying time for each coat? Making the duration 6 hours.


From: john reeve (2013-01-30 16:35)

Cement truck pulls up.
Dumps load. Workers spread and level. Then leave.

Duration: 2 days to dry before building
Craft effort: 3 guys for 4 hours
Sent on the Sprint� Now Network from my BlackBerry�

-----Original Message-----
From: "Thomas" <tcoulomb@scgov.net>
Sender: MAXIMO@yahoogroups.com
Date: Wed, 30 Jan 2013 16:32:56
To: <MAXIMO@yahoogroups.com>
Reply-To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] Job Plan Duration vs. labor hours

We are having the debate about job plan duration and planned labor hours on a job plan. Maximo doesn't have a very clear definition of what the duration is other than how many hours it will take to complete the work. Does/should this include time when work is not being

For example there is a work order to paint a small room with 2 coats of paint. Planning for 1 painter and 1 hour of labor for each coat we have 2 total labor hours. Is that the Duration? Or should we account for 2 hours of drying time for each coat? Making the duration 6 hours.



From: Kevin Egolf (2013-01-30 16:55)

Planned labor hours are used for resource planning. What craft, how many people and many hours will the work to accomplish the task.
Duration is how long will the job take from start to finish. This would include wait time, time for inspections and other non-working time (paint drying, concrete curing etc.) that is required by the job.
The duration is useful in scheduling subsequent tasks and is used to set the target finish and scheduled finish dates.
V/R
Kevin
-----Original Message-----
From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of john reeve
Sent: Wednesday, January 30, 2013 11:36 AM
To: MAXIMO@yahoogroups.com
Subject: Re: [MAXIMO List] Job Plan Duration vs. labor hours
Cement truck pulls up.
Dumps load. Workers spread and level. Then leave.
Duration: 2 days to dry before building
Craft effort: 3 guys for 4 hours
Sent on the Sprint(r) Now Network from my BlackBerry(r)
-----Original Message-----
From: "Thomas" <tcoulomb@scgov.net>
Sender: MAXIMO@yahoogroups.com
Date: Wed, 30 Jan 2013 16:32:56
To: <MAXIMO@yahoogroups.com>
Reply-To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] Job Plan Duration vs. labor hours
We are having the debate about job plan duration and planned labor hours on a job plan. Maximo doesn't have a very clear definition of what the duration is other than how many hours it will take to complete the work. Does/should this include time when work is not being
For example there is a work order to paint a small room with 2 coats of paint. Planning for 1 painter and 1 hour of labor for each coat we have 2 total labor hours. Is that the Duration? Or should we account for 2 hours of drying time for each coat? Making the duration 6 hours.

------------------------------------
Email addresses you might need:
Posting: MAXIMO@yahoogroups.com
Join : MAXIMO-subscribe@yahoogroups.com
Leave : MAXIMO-unsubscribe@yahoogroups.com
Cry : MAXIMO-owner@yahoogroups.com
Group : http://groups.yahoo.com/group/MAXIMOYahoo! Groups Links