I have a PM that has a route with nine (9) assets. I setup the Route to list all nine assets under the Multiple Asset section of the work order. The Job Plan for the PM show 1.5 hours in the duration field. Because there are nine stops on the route, shouldn't the generated PM Work Order show 13.5 (9*1.5) hours in the Duration field? It only show 1.5?
Am I missing a parameter somewhere (i.e. Job Plan, Route and/or PM) that is causing this not to multiple or does the Job Plan duration need to be based on the number of assets in the route? This would seem old because I would then have to setup a different job plan based on the number of assets so I could adjust the duration.
Any ideas?
Steve
PS We are currently running version 7.1.1.11
No, the Job Plan duration is just that, how long from start to finish to do this job particular job. The duration on the Job Plan is just a straight crossover to work order. If you want it to do something special with it, you have to build something to do that, like an automation script or a java class.
Sean Clark-McCarthy
Sr. Solutions Architect
Cohesive Information Solutions
smccarthy@cohesivesolutions.com
________________________________
From: MAXIMO@yahoogroups.com [MAXIMO@yahoogroups.com] on behalf of ssentz74 [ssentz@pgov.com]
Sent: Thursday, March 07, 2013 2:10 PM
To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] Work Order Duration for PMs
I have a PM that has a route with nine (9) assets. I setup the Route to list all nine assets under the Multiple Asset section of the work order. The Job Plan for the PM show 1.5 hours in the duration field. Because there are nine stops on the route, shouldn't the generated PM Work Order show 13.5 (9*1.5) hours in the Duration field? It only show 1.5?
Am I missing a parameter somewhere (i.e. Job Plan, Route and/or PM) that is causing this not to multiple or does the Job Plan duration need to be based on the number of assets in the route? This would seem old because I would then have to setup a different job plan based on the number of assets so I could adjust the duration.
Any ideas?
Steve
PS We are currently running version 7.1.1.11