This is an archive of the Maximo Yahoo Community. The content of this pages may be a sometimes obsolete so please check post dates.
Thanks to the community owner Christopher Wanko for providing the content.
Hello everyone,
I'm wondering if there is a way to change the next due date on a pm?
We are on version 6.2.1(Oil & Gas).
I've read that it can be done on the newer versions of Maximo.
The only way I have accomplished this so far is by performing an update using SQL.
I would like to have the planner change the dates on the pm's they created.
Thx in advance,
mrggutz
Extend date will allow you to change when the next PM will generate. Check the box under the extend date will change the due date from next generation forward..
Shannon Sutton
Cell: (318) 334-8002
On May 23, 2013, at 8:59 PM, "George" <ggutierrez@pasadenarefining.com> wrote:
> Hello everyone,
> I'm wondering if there is a way to change the next due date on a pm?
> We are on version 6.2.1(Oil & Gas).
> I've read that it can be done on the newer versions of Maximo.
> The only way I have accomplished this so far is by performing an update using SQL.
>
> I would like to have the planner change the dates on the pm's they created.
>
> Thx in advance,
> mrggutz
>
>