Meter Based PM-WO target start date

From: mutss1 (2013-05-29 15:51)

I have created a meter based PM that generates a work order when the meter reaches 1000. The work order generates with a target equal to the date and time the work order was generated. Is there a way to have the work order generate when the meter reading is reached but with a work order target start date in the future?


From: Bill (2013-05-29 19:39)

Look on the Frequency tab > Meter Based Freq sub tab. Enter a value in the "Generate WO Ahead By" field. This works for Meter Based PMs just like the lead time value for time based PMs. The formula will be (meter based PM lead time in days) = [(Generate WO ahead by)/(Average Units per Day)]. Also make sure the "Generate WO When Meter Freq is Reached" checkbox is unchecked.
Bill Murphy
Grifols
v7.1.1.6
--- In MAXIMO@yahoogroups.com, "mutss1" <mutss1@...> wrote:
>
> I have created a meter based PM that generates a work order when the meter reaches 1000. The work order generates with a target equal to the date and time the work order was generated. Is there a way to have the work order generate when the meter reading is reached but with a work order target start date in the future?
>