Maximo trouble with Windows 8.1?

From: (2014-04-21 14:55)

I have a vendor who says she cannot enter long descriptions in Work Logs since upgrading.


From: Juniko (2014-04-22 06:56)

Dear All,
I have many lines in material work plan with the spesific ordering.
But when I do reorder process to be one PR manually, I find that the specific order of material changed by maximo.
Regards,
Juniko


From: Juniko (2014-04-22 07:25)

> Dear All,
>
> I have many lines in material work plan with the spesific ordering.
> But when I do reorder process to be one PR manually, I find that the specific order of material changed by maximo.
>
> Regards,
> Juniko


From: (2014-04-21 20:30)

Dear All,

I have many lines in material work plan with the spesific ordering.
But when I do reorder process to be one PR manually, I find that the specific order of material changed by maximo.
Any one know how to fix it.
I use maximo 7.5.0.3 but might be same problem in other version.

Regards,
Juniko


From: Klemenok, Eric (2014-04-22 13:52)

It’s obviously being sorted on some field, so is it via ITEMNUM or what ?


From: MAXIMO@yahoogroups.com [mailto:MAXIMO@yahoogroups.com] On Behalf Of juniko@gmail.com
Sent: Monday, April 21, 2014 10:31 PM
To: MAXIMO@yahoogroups.com
Subject: [MAXIMO List] different order between plan material and pr



Dear All,

I have many lines in material work plan with the spesific ordering.
But when I do reorder process to be one PR manually, I find that the specific order of material changed by maximo.
Any one know how to fix it.
I use maximo 7.5.0.3 but might be same problem in other version.

Regards,
Juniko