Re: [MAXIMO List] PM Next Due Date

From: ggutierrez (2013-05-23 21:45)

Thx I will try that in the morning.
The sender of this message is responsible for its content and addressing. Any actions not conforming to Petrobras System internal policies are forbidden.
----- Original Message -----
From: Yahoo [shannonsuttondale@yahoo.com]
Sent: 05/23/2013 09:25 PM EST
To: "MAXIMO@yahoogroups.com" <MAXIMO@yahoogroups.com>
Subject: Re: [MAXIMO List] PM Next Due Date
Extend date will allow you to change when the next PM will generate. Check the box under the extend date will change the due date from next generation forward..
Shannon Sutton
Cell: (318) 334-8002
On May 23, 2013, at 8:59 PM, "George" <ggutierrez@pasadenarefining.com> wrote:
> Hello everyone,
> I'm wondering if there is a way to change the next due date on a pm?
> We are on version 6.2.1(Oil & Gas).
> I've read that it can be done on the newer versions of Maximo.
> The only way I have accomplished this so far is by performing an update using SQL.
>
> I would like to have the planner change the dates on the pm's they created.
>
> Thx in advance,
> mrggutz
>
>


From: Bill (2013-05-24 11:30)

One other note about the Extend Date function in v6... The field label is a bit misleading. You can actually set it for an earlier date as well if that need arises. I have not tried this in v7 yet, but I know it worked when we were on v6.
Bill Murphy
Grifols
v7.1.1.6
--- In MAXIMO@yahoogroups.com, ggutierrez@... wrote:
>
> Thx I will try that in the morning.
>
> The sender of this message is responsible for its content and addressing. Any actions not conforming to Petrobras System internal policies are forbidden.
>
>
> ----- Original Message -----
> From: Yahoo [shannonsuttondale@...]
> Sent: 05/23/2013 09:25 PM EST
> To: "MAXIMO@yahoogroups.com" <MAXIMO@yahoogroups.com>
> Subject: Re: [MAXIMO List] PM Next Due Date
>
>
>
> Extend date will allow you to change when the next PM will generate. Check the box under the extend date will change the due date from next generation forward..
>
>
>
> Shannon Sutton
> Cell: (318) 334-8002
>
> On May 23, 2013, at 8:59 PM, "George" <ggutierrez@...> wrote:
>
> > Hello everyone,
> > I'm wondering if there is a way to change the next due date on a pm?
> > We are on version 6.2.1(Oil & Gas).
> > I've read that it can be done on the newer versions of Maximo.
> > The only way I have accomplished this so far is by performing an update using SQL.
> >
> > I would like to have the planner change the dates on the pm's they created.
> >
> > Thx in advance,
> > mrggutz
> >
> >
>
>
>
>
>
>
>
>


From: foundationboarder187 (2013-05-24 12:11)

In Maximo 6, the help tools is very usefull for extended date. It will walk you through the process. What I normally do when I need to change the next due date is:
1. Set an extended date for the next time the pm is due.
2. Run the WO Gen for that date (there's a popup box when running Wo Gen where you can set the days out to the next time the PM is needed)
3. Recheck the box for "use last workorder start date to calculate..."
4. Click Save.
5. Grab yourself a cup of coffee :)
The estimated next due date should also reflect the changes.
Thanks,
Todd
--- In MAXIMO@yahoogroups.com, "Bill" <bill.e.murphy@...> wrote:
>
> One other note about the Extend Date function in v6... The field label is a bit misleading. You can actually set it for an earlier date as well if that need arises. I have not tried this in v7 yet, but I know it worked when we were on v6.
>
> Bill Murphy
> Grifols
> v7.1.1.6
>
> --- In MAXIMO@yahoogroups.com, ggutierrez@ wrote:
> >
> > Thx I will try that in the morning.
> >
> > The sender of this message is responsible for its content and addressing. Any actions not conforming to Petrobras System internal policies are forbidden.
> >
> >
> > ----- Original Message -----
> > From: Yahoo [shannonsuttondale@]
> > Sent: 05/23/2013 09:25 PM EST
> > To: "MAXIMO@yahoogroups.com" <MAXIMO@yahoogroups.com>
> > Subject: Re: [MAXIMO List] PM Next Due Date
> >
> >
> >
> > Extend date will allow you to change when the next PM will generate. Check the box under the extend date will change the due date from next generation forward..
> >
> >
> >
> > Shannon Sutton
> > Cell: (318) 334-8002
> >
> > On May 23, 2013, at 8:59 PM, "George" <ggutierrez@> wrote:
> >
> > > Hello everyone,
> > > I'm wondering if there is a way to change the next due date on a pm?
> > > We are on version 6.2.1(Oil & Gas).
> > > I've read that it can be done on the newer versions of Maximo.
> > > The only way I have accomplished this so far is by performing an update using SQL.
> > >
> > > I would like to have the planner change the dates on the pm's they created.
> > >
> > > Thx in advance,
> > > mrggutz
> > >
> > >
> >
> >
> >
> >
> >
> >
> >
> >
>


From: ggutierrez (2013-05-24 07:14)

Thanks for the help that worked like a charm....

Have a great weekend everyone.



Thank You,

George Gutierrez Jr.
Maximo Administration
Pasadena Refining Systems
713.920.3908 Direct
832.473.5330 Cell
U1O2 - Chave



From: "Bill" <bill.e.murphy@grifols.com>
To: MAXIMO@yahoogroups.com
Date: 05/24/2013 06:31 AM
Subject: Re: [MAXIMO List] PM Next Due Date
Sent by: MAXIMO@yahoogroups.com






One other note about the Extend Date function in v6... The field label is a
bit misleading. You can actually set it for an earlier date as well if that
need arises. I have not tried this in v7 yet, but I know it worked when we
were on v6.

Bill Murphy
Grifols
v7.1.1.6

--- In MAXIMO@yahoogroups.com, ggutierrez@... wrote:
>
> Thx I will try that in the morning.
>
> The sender of this message is responsible for its content and addressing.
Any actions not conforming to Petrobras System internal policies are
forbidden.
>
>
> ----- Original Message -----
> From: Yahoo [shannonsuttondale@...]
> Sent: 05/23/2013 09:25 PM EST
> To: "MAXIMO@yahoogroups.com" <MAXIMO@yahoogroups.com>
> Subject: Re: [MAXIMO List] PM Next Due Date
>
>
>
> Extend date will allow you to change when the next PM will generate.
Check the box under the extend date will change the due date from next
generation forward..
>
>
>
> Shannon Sutton
> Cell: (318) 334-8002
>
> On May 23, 2013, at 8:59 PM, "George" <ggutierrez@...> wrote:
>
> > Hello everyone,
> > I'm wondering if there is a way to change the next due date on a pm?
> > We are on version 6.2.1(Oil & Gas).
> > I've read that it can be done on the newer versions of Maximo.
> > The only way I have accomplished this so far is by performing an update
using SQL.
> >
> > I would like to have the planner change the dates on the pm's they
created.
> >
> > Thx in advance,
> > mrggutz
> >
> >
>
>
>
>
>
>
>
>